WHAT HAVE BEEN ACCOMPLISHED:

JMEC has been structural engineer for a school corridor safety improvement project in the City of Concord.

JMEC designed a precast pretensioned slab bridge to replace an existing timber bridge and widened the existing bridge over Contra Costa Canal.  Design considered East Bay Water District requirements and other environmental impacts to the canal.

During construction, JMEC reviewed pretresssing shop drawings and concrete mix design, performed site visits, and evaluated test results.

The construction of the replacement bridge was completed in less than 4 weeks, and the entire project was completed on budget and on schedule in the summer of 2004.
Project Role:  Bridge Design Consultant

Clients:  City of Concord

Schedule:  Construction was completed in 2004